Flagler County to Pick $37M-$85M Beach Restoration Plan This Month
Flagler County commissioners, meeting Wednesday, Nov. 11, 2026, are weighing three proposals to replenish sand and rebuild dunes along roughly 6 miles of coastline damaged by king tides and a nor'easter. Options include trucking inland sand (about $85 million), ocean-floor dredging (about $61 million), and a dredging-plus-beach-widening plan with an initial cost of about $37 million that could add hundreds of millions in environmental mitigation, according to coastal engineer Casey Connor of Moffatt & Nichol. Commissioners raised concerns about environmental impacts and permitting for the widening option, and discussion appeared to lean toward the dredging proposal, though no final decision has been made. The county's goal is to select a plan this month and submit permit applications by next spring.