Roseville Park Bids Top Budget by $312,000; New Bidding Planned for Late December
The Roseville City Council voted Nov. 4 to reject all four construction bids for Michael Ziegler Park, a planned 1.7-acre neighborhood park at Starfield Drive and Nova Place in the Sierra Vista neighborhood, after bids ranged from $912,409 to more than $1.14 million against a $600,000 budget. City staff revised the plans — narrowing sidewalks, reducing planting and irrigation areas, and scaling back concrete features — lowering the estimated base construction cost to $525,000. The city will reopen bids in late December, with staff expected to return to the council in January for contract approval; construction is targeted for early spring 2027. Optional amenities such as a half-court basketball area and a shade structure could be excluded if costs remain high, and the project is funded by development fees rather than the general fund.