Coconut Creek's plan to replace the temporary trailer that houses Fire Rescue Station 113 has reached 30% design, according to a staff report and presentation prepared for the City Commission's Nov. 12 meeting. The item was listed as a design progress report, not a vote.
Station 113 now operates from a temporary trailer just south of Wiles Road and east of State Road 7, and the city's Fire Administration staff works in leased office space. The staff report says a permanent station is needed to serve the upcoming MainStreet area. The combined building would go on part of a vacant 10-acre city-owned parcel along Cullum Road.
The commission hired Currie Sowards Aguila Architects on Aug. 28, 2025, to design the facility. According to the staff report, estimates from Pirtle Construction Company, the construction manager at risk, show the project remains within budget.
The presentation lists four apparatus bays, bunk rooms, a kitchen and day room, a gym, a decontamination room and a training tower for the station, plus offices, a conference room and a multipurpose training room for fire administration. It describes the building as CAT5-rated with 100% emergency power, and the plans show a linear park along Cullum Road and a solar carport.
Cost and borrowing
The presentation puts the permanent station at about $30.6 million, one of three capital priorities the commission identified in fiscal 2024, along with about $41.6 million in police department improvements and about $9.4 million for MainStreet civic space and infrastructure. In fiscal 2025 the city chose revenue bonds to pay for them, with debt payments coming from Seminole Municipal Services Provider Agreement revenues, up to available capacity, and general fund revenues. That year the city raised its property tax rate by 0.4525 mills, from 6.4463 to 6.8988, to support general fund needs, according to the presentation.
The plan calls for a $26 million first bond phase in fiscal 2027 for the fire station and a $54 million second phase in fiscal 2028 covering the rest of the station, MainStreet and police improvements. The timeline shows the bond ordinance coming to the commission for first and second readings in May 2027, the bond closing in June 2027 and construction starting in July 2027.
The documents do not estimate total interest costs or the effect on individual taxpayers, and this report has not confirmed what was said at the Nov. 12 meeting.