The Marion County Board of County Commissioners on Nov. 3 approved a $268,740 task order with Kimley-Horn and Associates Inc. of Ocala to design the second phase of a Safe Routes to School sidewalk project for the Belleview Middle School area. The item was part of the consent agenda, which commissioners approved 5-0 on a motion by Commissioner Stone, seconded by Commissioner Curry, according to the county's Legistar records.

According to the county procurement memo, Kimley-Horn was selected on Dec. 3, 2024, to help the county apply to the Florida Department of Transportation's Safe Routes to School program in two phases. Phase 1 covers sidewalk improvements near Belleview Middle School and Belleview High School to fill gaps and extend the existing sidewalk network. Phase 2 would add sidewalks north of Phase 1 to tie into the existing sidewalk network on US 301/US 441.

On Sept. 24, 2025, FDOT awarded the county funding for Phase 1 only, with design programmed for FDOT's fiscal year 2029 and construction for fiscal year 2031, the memo says. The county is now paying for Phase 2 design itself, from its Sidewalk Construction Fund and second local option fuel tax money.

The Phase 2 work generally extends along SE 36th Avenue from SE 98th Place to SE 95th Street to US 441. Kimley-Horn's scope includes surveying and mapping, traffic data collection, an environmental assessment, sidewalk and lighting design, utility coordination, signing and pavement markings, ADA-compliant driveway crossings, an evaluation of existing roadside drop-off conditions, permitting coordination, and construction plans and cost estimates.

The approval covers design only. The memo does not identify money or a schedule for building Phase 2, and it does not explain why FDOT funded only the first phase.