Commission directs contract negotiations with top-ranked firm
The Pembroke Pines City Commission approved File 26-3084 at its Nov. 4, 2026 regular meeting, adopting the evaluation committee's findings for RFQ #PSUT-25-14, "CCNA Sunswept Community Water System Replacement Program." Under Florida's Consultants' Competitive Negotiation Act, the motion awards the work to the highest-ranked vendor, Chen Moore and Associates, Inc., and directs the City Manager to negotiate a contract for services. This is a selection and authorization to negotiate, not an executed contract. The city's Legistar record shows the file created Oct. 22, on the Nov. 4 agenda, with status Passed and final action Nov. 4; the city's meeting page did not yet show finalized minutes or action results.
What the design work covers
According to the RFQ issued Feb. 10, 2026, the program will replace aging potable water mains in the Sunswept residential community and adjacent commercial areas under the city's 5-Year Capital Improvement Plan. The consultant will provide engineering design and professional engineering services during construction, acting as Engineer of Record for traditional Design-Bid-Build delivery. The design covers replacement of water mains and services, upsizing of undersized pipes, relocation of rear-yard water meters to the right-of-way, new meters and meter boxes, dual check valves, replacement of existing fire hydrants, abandonment of old mains, and restoration or resurfacing. Construction methods under consideration include open cut, Close Tolerance Pipe Slurrification and pipe bursting, per Addendum No. 1 issued March 5, 2026.
In the RFQ's question-and-answer report, the city said the project lies within the "Boulevard Heights Section Nine," also known as Sunswept, generally bounded by Taft Street to the north, Johnson Street to the south, University Drive to the east and Douglas Road to the west. It put the total water main to be replaced at approximately 58,100 linear feet. The mains include asbestos cement, PVC and galvanized steel pipe.
Costs: staff estimates, fee still to be negotiated
City staff estimated the related Capital Improvement Project at $15,120,000 in total, including an estimated $14,000,000 for construction and $1,120,000 for professional services. The RFQ says that professional-services solicitation covers both engineering design and engineering services during the construction phase. These are staff estimates, not a negotiated price. The RFQ states grant and federal funding is "Not applicable." Because the selection was made under CCNA, firms did not compete on price: the fee is to be negotiated with Chen Moore, and if the city cannot reach a price it considers fair, competitive and reasonable, it must formally terminate negotiations and begin talks with the next-ranked firm.
How the bidders scored
Ten firms responded by the March 24, 2026 deadline. A five-member evaluation committee, listed in the tabulation as Assistant City Engineer John England, Project Manager Laura Eusse, Professional Engineer Armando Godoy, Senior Project Manager Fernando Pleitez and Assistant Utilities Director Paul Thompson, scored proposals in two phases. In Phase 1 aggregate scores, BCC Engineering LLC led with 84 points, ahead of Chen Moore and Kimley-Horn at 83 each. In the Phase 2 tabulation Chen Moore finished first at 86.38 out of 100, 0.28 points ahead of Kimley-Horn (86.10), with BCC third at 83.79. The other seven firms are shown as excluded with zero scores in Phase 2.
Timeline and what's still unknown
The RFQ projected an 18-month design period with an estimated start of Aug. 1, 2026 and completion by Feb. 1, 2028. That estimated start predates the Nov. 4 selection, and the reviewed records do not state a revised schedule. The records reviewed also do not state how many homes are affected, and construction dates will depend on a negotiated contract, completed design and future bid awards.