Ocala City Council on Nov. 3 approved Budget Resolution 2027-104, appropriating the remaining $718,476 of a $1,436,953 Florida Department of Environmental Protection grant for the Foxwood Farms sewer expansion project. The city had previously appropriated the other $718,477.

The resolution was adopted on a 5-0 roll call after Council Member Kristen M. Dreyer moved it and James P. Hilty Sr. seconded, according to the city's Legistar records. Jay A. Musleh, Barry Mansfield and Council President Ire J. Bethea Sr. also voted yes.

The project is designed to take out of service a package treatment plant that serves mixed-use residential lots and a community center in the Foxwood Farms subdivision, sending the wastewater instead to the city's Water Reclamation Facility No. 3 through a new sanitary sewer conveyance system, according to the city staff report. The developer, MHC Foxwood Farms LLC, is carrying out the work: the state agreed to reimburse the city up to $1,436,953, and the city passes that money through to the developer for approved tasks. The developer has agreed to provide the documentation the grant requires for quarterly reports and reimbursements.

The state has deemed Rainbow Springs an impaired water body, in part because of elevated nitrate levels, the staff report says. City staff estimate that connecting Foxwood Farms to central sewer will remove about 5,491 pounds of total nitrogen a year from the Rainbow Springs Basin Management Action Plan area.

The developer expects to complete the job by January 2027, according to the staff report. The grant agreement, first approved by the council on July 20, 2021, was extended twice — in March 2023 and April 2025 — and now expires Dec. 31, 2027.

The staff report and resolution do not say whether Foxwood Farms residents will pay connection fees or new monthly sewer charges, or how the change will affect their current service.