Marion County is moving ahead with design of a second set of sidewalks for students walking to Belleview Middle School, even though the state has agreed to pay only for the first phase.
The County Commission approved a $268,740 task order with Kimley-Horn and Associates of Ocala on Nov. 3 as part of its consent agenda, according to the county's online meeting records. The meeting minutes have not been finalized. The money comes from the county's Sidewalk Construction Fund and its second local option fuel tax.
According to the staff summary, the county hired Kimley-Horn in December 2024 to help apply for Florida Department of Transportation Safe Routes to School money in two phases. Phase 1 would fill gaps and extend sidewalks near Belleview Middle and Belleview High schools; Phase 2 would add sidewalks to the north to connect with the existing sidewalk network on US 301/US 441. On Sept. 24, 2025, FDOT funded Phase 1 only, with design programmed for its 2029 fiscal year and construction for fiscal 2031.
The Phase 2 design area runs along SE 36th Avenue from SE 98th Place north to SE 95th Street, and along SE 95th Street east to US 441, with sidewalks planned within the existing public right-of-way. The work includes surveying, traffic data, environmental review, sidewalk and lighting design, signs and pavement markings, ADA-compliant driveway crossings and an evaluation of existing roadside drop-off conditions. The draft task order calls for lighting analysis at two crosswalks on SE 95th Street, including a proposed midblock crosswalk.
Design is estimated to take 12 months from a start date the county and firm agree on. The county documents reviewed for this report, including the Phase 2 design task order, do not identify when or how Phase 2 construction would be paid for.