A solar feasibility study for the Town of Hillsborough found six buildings at five town-owned sites viable for rooftop solar panels. Together they could hold about 156 kilowatts of panels, producing about 199,980 kilowatt-hours a year and avoiding about 125 metric tons of carbon dioxide-equivalent emissions, according to the July 23 report by Pisgah Energy, which did the study with NV5. Town staff are scheduled to present the findings, along with an update on town energy use, to the Board of Commissioners at its 7 p.m. meeting Monday, Nov. 9, in the Town Hall Annex at 105 E. Corbin St. The board is asked only to receive the presentation.
The report puts the base budgets for the five projects at $658,631 in all, covering engineering, interconnection, construction and construction administration, and its budget table includes $197,589 in modeled federal direct-pay incentives. Those are estimates, not an approved expenditure or a secured award. The report's estimated payback periods, which assume the town receives that modeled incentive, run from 18.5 years for the Town Hall Annex and 19.7 years for the Adron F. Thompson Building to 29.7 years for the Motor Pool/86 N facility and more than 30 years for the water and wastewater treatment plants.
Five of the six roofs need to be evaluated for remaining useful life, and possibly replaced, before panels go on, the report says. Its table lists replacing the entire roof before solar at the Town Hall Annex, the Motor Pool/86 N facility and the water and wastewater plants. Only the new expansion section of the Adron F. Thompson Facility will be "solar ready," and the structural engineer doesn't recommend solar on that building's existing roof without remediation.
The report says local governments are currently eligible for a 30% federal direct-pay incentive, and it assumes solar projects must be placed in service by Dec. 31, 2027 to qualify. The report describes that as its planning deadline; this story does not independently confirm how the federal rules apply to the town's projects, and the report itself says eligibility also depends on limits on materials from "foreign entities of concern," with final Treasury guidance still awaited. Its next steps are for staff to decide which projects advance to design, replace roofs where needed, and seek construction bids once plans are complete. It recommends engineering and building several projects at once for economies of scale.
The town adopted a clean energy resolution in September 2017 committing to 80% clean and renewable energy by 2030 and 100% by 2050; the agenda abstract says Hillsborough was the first North Carolina municipality to make that commitment. The staff presentation reports a 30% decrease in Town Hall's electricity use from January 2022 to July 2026, and a 49.7% drop in streetlight energy use over five years after a switch to LED lights that began in 2022, even as streetlights were added. Fleet fuel use rose 16.7% over five years and fuel costs 13.8%, while police hybrid patrol cars improved fuel economy from 8 to 18-20 miles per gallon, it says.