Silicon Valley BART Extension Off Track for $12.7B Budget Target
Santa Clara Valley Transportation Authority officials disclosed that the four-station, 5-mile Silicon Valley BART extension to downtown San Jose and Santa Clara will exceed its $12.7 billion budget target, up from a $4.7 billion projection in 2014, with tunnel boring set to begin in early 2028 toward a 2037 service date. Officials cited tariffs, data-center construction competition, higher energy prices and a $700 million federal grant shortfall, and said stations may be phased or interim light rail evaluated; a full board presentation is planned for December. Separately, Bay Area voters approved Proposition RTM (61.5%-38.5%) and San Francisco's Proposition H (72.4%-27.6%), yet BART still projects a $57 million deficit even with about $310 million annually from RTM. Statewide, voters made the 12.3% income tax on high earners permanent via Proposition 3, expected to generate $5 billion-$15 billion a year for education.